[Step-by-Step] Joe used a project management software package and has determined the following results for a given project. Expected completion time of


Question: Joe used a project management software package and has determined the following results for a given project.

Expected completion time of the project = 22 days

Variance of project completion time = 2.77

What is the probability of completing the project within 20 days?

  1. 0.3849
  2. 0.8849
  3. 0.1151
  4. 0.7642
  5. 0.2358