Question: A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is
- 6.0
- 6.33
- 7.0
- 7.5
- 10.0