[See Steps] A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10
Question: A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is
- 7/9
- 7/6
- 1/3
- 2/3
- 1.0
Price: $2.99
Solution: The downloadable solution consists of 1 pages
Deliverable: Word Document
Deliverable: Word Document
