(See Solution) The following information is available for three MPS items: Product A: An 80-unit order is to be started in week 3. A 55-unit order is to be


Question: The following information is available for three MPS items:

Product A: An 80-unit order is to be started in week 3. A 55-unit order is to be started in week 6.

Product B: A 125-unit order is to be started in week 5.

Product C: A 60-unit order is to be started in week 4.

Develop the material requirements plan for the next 6 weeks for items D, E, and F. The BOMs and inventory records are shown here:

Item
Data Category D E F
Lot-sizing rule FOQ=150 L4L POQ (P=2)
Lead time 3 weeks 1 week 2 weeks
Safety Stock 0 0 30
Scheduled Receipts 150 (week 3) 120 (week 2) None
Beginning Inventory 150 0 100

Price: $2.99
Solution: The downloadable solution consists of 3 pages
Deliverable: Word Document