(See Solution) The following information is available for three MPS items: Product A: An 80-unit order is to be started in week 3. A 55-unit order is to be
Question: The following information is available for three MPS items:
Product A: An 80-unit order is to be started in week 3. A 55-unit order is to be started in week 6.
Product B: A 125-unit order is to be started in week 5.
Product C: A 60-unit order is to be started in week 4.
Develop the material requirements plan for the next 6 weeks for items D, E, and F. The BOMs and inventory records are shown here:
| Item | |||
| Data Category | D | E | F |
| Lot-sizing rule | FOQ=150 | L4L | POQ (P=2) |
| Lead time | 3 weeks | 1 week | 2 weeks |
| Safety Stock | 0 | 0 | 30 |
| Scheduled Receipts | 150 (week 3) | 120 (week 2) | None |
| Beginning Inventory | 150 | 0 | 100 |