The following jobs are waiting to be processed at your work center, which cleans valve body castings
Question: The following jobs are waiting to be processed at your work center, which cleans valve body castings. Job numbers are assigned sequentially upon arrival in the facility (a missing number means that job does not require your work center). All dates are specified as days from Today.
Job | Due Date | Duration (days) |
101 | 43 | 10 |
102 | 34 | 12 |
104 | 37 | 11 |
107 | 32 | 7 |
108 | 37 | 15 |
a. In what sequence should the jobs be processed according to the FCFS scheduling rule?
b. In what sequence should the jobs be processed according to the EDD scheduling rule?
c. In what sequence should the jobs be processed according to the SPT scheduling rule?
d. In what sequence should the jobs be processed according to the LPT scheduling rule?
e. In what sequence should the jobs be processed according to the critical ratio scheduling rule?