(page 90 in the text) a. Draw the activity on node (AON) project network associated with
Question: Problem 3.3 (page 90 in the text)
a. Draw the activity on node (AON) project network associated with the following activities for Dave Carharts consulting company project. How long should it take Dave and his team to complete this project? What are the critical path activities?
Activity | Immediate Predecessors | Time (Days) |
A | ____ | 3 |
B | A | 4 |
C | A | 6 |
D | B | 6 |
E | B | 4 |
F | C | 4 |
G | D | 6 |
H | E,F | 8 |