A machine set to fill a bottle with 60.0 grams of liquid was started at 7:00 a.m. today. Slight vari
Question: A machine set to fill a bottle with 60.0 grams of liquid was started at 7:00 a.m. today. Slight variations (called chance variation or sampling fluctuation) were expected. The quality control inspector made her initial check of the weights at 8:00 a.m. She selected a five bottles from the first hour of production and weighed the contents of each bottle. The results of the first seven inspections follow;
| Time | 1 | 2 | 3 | 4 | 5 |
| 8 a.m. | 60.0 | 59.9 | 60.0 | 60.0 | 60.1 |
| 9 a.m. | 60.0 | 60.2 | 60.1 | 60.2 | 60.0 |
| 10 a.m. | 60.1 | 60.1 | 60.0 | 59.8 | 60.0 |
| 11 a.m. | 60.0 | 59.8 | 60.0 | 60.0 | 60.2 |
| 12 noon | 60.2 | 60.0 | 59.8 | 60.1 | 59.8 |
| 1 p.m. | 60.3 | 60.1 | 59.9 | 60.1 | 59.8 |
| 2 p.m. | 60.1 | 59.8 | 59.7 | 59.9 | 59.8 |
a) Compute the lower and upper control limits for the sample means
b) Construct a control chart for the sample means.
c) Is the process in control? Explain!