[Solution Library] The time to complete a construction project is normally distributed with a mean of 45 weeks and standard deviation of 4.5 weeks. What is
Question: The time to complete a construction project is normally distributed with a mean of 45 weeks and standard deviation of 4.5 weeks.
- What is probability the project will be finished in 53 weeks or less?
- What is the probability the project will be finished in 40 weeks or less?
- What is probability the project will take more than 57 weeks?