(See) A manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of 33^1 / 3 units. Assume the shop works


Question: A manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of \(33^{1} / 3\) units. Assume the shop works a 60 -minute hour. Assign the tasks shown in the $8 c$ companying precedence diagram (times are in minutes) to workstations using the following rules:

  1. In order of most following tasks. Tiebreaker: greatest positional weight.
  2. In order of greatest positional weight.
  3. What is the efficiency?