Question: A time study was conducted on a job that contains four elements. The observed times and performance ratings for six cycles are shown in the following table.
| Element | Rating | 1 | 2 | 3 | 4 | 5 | 6 |
| 1 | 0.9 | 0.44 | 0.5 | 0.43 | 0.45 | 0.48 | 0.46 |
| 2 | 0.85 | 1.5 | 1.54 | 1.47 | 1.51 | 1.49 | 1.52 |
| 3 | 1.1 | 0.84 | 0.89 | 0.77 | 0.83 | 0.85 | 0.8 |
| 4 | 1 | 1.1 | 1.14 | 1.08 | 1.2 | 1.16 | 1.26 |
- Determine the average cycle time.
- Find the normal time for each element.
c Assuming an allowance factor of 15 percent of job time, compute the standard time for this job.