Question: Jean Walker is making plans for spring break at the beaches in Florida. In applying technique she learned in her quantitative methods class, she has identified the activities that are necessary to prepare for her trip. The following table lists the activities and the immediate predecessors. Draw the network for this project.

Activity Immediate Predecessors
A
B A
C A
D B
E C,D
F A
G E,F

The following are the activity times for Jean Walkers activities. Find the earliest, latest, and slack times for each activity. Then find the critical path.

Activity Time (in days)
A 3
B 7
C 6
D 2
E 5
F 8
G 4

Price: $2.99
Solution: The downloadable solution consists of 2 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in