[See Steps] The air pollution project discussed in the chapter has progressed over the past several weeks, and it is now the end of week 8. Lester Harky
Question: The air pollution project discussed in the chapter has progressed over the past several weeks, and it is now the end of week 8. Lester Harky would like to know the value of the work completed, the amount of any cost overruns or under runs for the project, and the extent to which the project is ahead of or behind schedule by developing a table like Table 11.8. The revised cost figures are shown in the following table:
| Activity | Percent of Completion | Actual Cost ($) |
| A | 100 | 20,000 |
| B | 100 | 36,000 |
| C | 100 | 26,000 |
| D | 100 | 44,000 |
| E | 50 | 25,000 |
| F | 60 | 15,000 |
| G | 10 | 5,000 |
| H | 10 | 1,000 |
Deliverable: Word Document 