[Solution Library] The following are the operation times and due dates for five jobs (each job undergoes a single operation): Job Processing Time (days) Due Date
Question: The following are the operation times and due dates for five jobs (each job undergoes a single operation):
| Job | Processing Time (days) |
Due Date
(days hence) |
| A | 6 | 8 |
| B | 2 | 6 |
| C | 8 | 18 |
| D | 3 | 15 |
| E | 9 | 23 |
The firm operates seven days per week. Assign the jobs according to each of the following priority rules:
- shortest operation time (SOT)
- earliest due date (EDD)
- slack time remaining (STR)
- critical ratio (CR)
Evaluate each of the above priority rules with the objective of minimizing the mean
tardiness
. The term
tardiness
is used here, rather than
lateness
, to indicate that there is no credit for a job completed early. A job completed early simply has a
tardiness
value of 0. In other words,
lateness
and
tardiness
are the same if the job is completed after the due date, but different if the job is completed before the due date. For minimizing mean tardiness, no rule is best under all circumstances.
Which one of the priority rules did you determine to be best in this particular case?