Question: The following are the operation times and due dates for five jobs (each job undergoes a single operation):

Job Processing Time (days) Due Date
(days hence)
A 6 8
B 2 6
C 8 18
D 3 15
E 9 23


The firm operates seven days per week. Assign the jobs according to each of the following priority rules:

  1. shortest operation time (SOT)
  2. earliest due date (EDD)
  3. slack time remaining (STR)
  4. critical ratio (CR)

Evaluate each of the above priority rules with the objective of minimizing the mean tardiness . The term tardiness is used here, rather than lateness , to indicate that there is no credit for a job completed early. A job completed early simply has a tardiness value of 0. In other words, lateness and tardiness are the same if the job is completed after the due date, but different if the job is completed before the due date. For minimizing mean tardiness, no rule is best under all circumstances.

Which one of the priority rules did you determine to be best in this particular case?

Price: $2.99
Solution: The downloadable solution consists of 3 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in