[All Steps] Davis Industries is installing a new computer system. After reviewing the activity times and costs, the vendor has the following information,
Question: Davis Industries is installing a new computer system. After reviewing the activity times and costs, the vendor has the following information, cost and time estimates of the project:
| Time (Weeks) | Cost ($) | ||||
| Activity | Normal | Crash | Normal | Crash | Predecessor |
| A | 3 | 1 | 900 | 1700 | - |
| B | 6 | 3 | 2000 | 4000 | - |
| C | 2 | 1 | 500 | 1000 | A |
| D | 5 | 3 | 1800 | 2400 | B, C |
| E | 4 | 3 | 1500 | 2350 | D |
| F | 3 | 1 | 3000 | 4900 | E |
| G | 9 | 4 | 8000 | 12800 | B, C |
| H | 3 | 2 | 1000 | 2200 | F, G |
The contractor will incur a $425 per week penalty for each week the project lasts beyond week 16.
- Find the critical path for minimum cost schedule.
- Which activities will crash to minimize the costs and for how long?
Price: $2.99
Solution: The downloadable solution consists of 2 pages
Deliverable: Word Document 