Given the following network and activity time estimates, determine earliest and latest activity time


Question: Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion tiMeand variance, and the probability that the project will be completed in 27 days or less.

Time Estimates (Days)
Activity a m b
1 5 8 15
2 7 10 12
3 3 5 6
4 1 3 6
5 4 6 7
6 3 3 3
7 3 4 6