Given the following history of problems found and fixed (i.e. new and closed) during the first ten w


Question: Given the following history of problems found and fixed (i.e. new and closed) during the first ten weeks of a project.
a) Plot the BMI versus time with a run chart.
b) Is the project doing well at resolving problems? Explain.
c) What is the trend for the future? Explain.
d) What is the cumulative number of problems unresolved at the end of this ten week period?

Week # new problems # closed problems
1 8 3
2 11 6
3 9 7
4 11 8
5 14 11
6 14 12
7 21 17
8 17 14
9 13 11
10 14 13
Price: $2.99
Solution: The solution consists of 4 pages
Deliverables: Word Document