You have just determined the actual number of workstations that will be used on an assembly line to


Question: You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure. The cycle time of the line is 10 minutes and the sum of all the tasks required on the line is 60 minutes. What is the correct value for the resulting line's efficiency?

Price: $2.99
Answer: The solution consists of 1 page