A farm owner is going to erect a maintenance building with a connecting electrical generator and wat


Question: A farm owner is going to erect a maintenance building with a connecting electrical generator and water tank. The activities, activity descriptions, and estimated durations are given in the following table. Construct the AON network for this project, identify the critical path, and determine the project duration time. (Note the times are in weeks)

Activity Activity Description Predecessor Duration
a Excavate - 2
b Erect building a 6
c Install generator a 4
d Install tank a 2
e Install maintenance equipment b 4
f Connect generator and tank to building b,c,d 5
g Paint finish b 3
h Check out facility e,f 2