The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Ea
Question: The MPS calls for 50 units of Product A and 60 of B. There are currently 35 of Product B on hand. Each A requires 2 of Part C; each B requires 5 of C. There are 160 units of C available.
a. Calculate the net requirements for B.
b. Calculate the gross requirements for C.
c. Calculate the net requirements for C.