The following is the activity and associated costs for the renovation of the local high school footb


Question: The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.

Activity Immediate Predecessor Time Cost ($)
A - 4 25000
B - 5 30000
C A 3 15000
D B 8 50000
E B 2 12000
F C, D 3 15000
G C, D 7 46000
H E, F 2 20000

a. What is the critical path for this project?

b. How much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?