The following is the activity and associated costs for the renovation of the local high school footb
Question: The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.
Activity | Immediate Predecessor | Time | Cost ($) |
A | - | 4 | 25000 |
B | - | 5 | 30000 |
C | A | 3 | 15000 |
D | B | 8 | 50000 |
E | B | 2 | 12000 |
F | C, D | 3 | 15000 |
G | C, D | 7 | 46000 |
H | E, F | 2 | 20000 |
a. What is the critical path for this project?
b. How much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?
Price: $2.99
Answer: The solution file consists of 3 pages
Deliverables: Word Document
Deliverables: Word Document