Embassy Club Condos, located on the West coast of Florida, is undertaking a summer renovation of its
Question: Embassy Club Condos, located on the West coast of Florida, is undertaking a summer renovation of its main bldg. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
Activity | Immediate Predecessor | Time |
A | --- | 3 |
B | --- | 1 |
C | --- | 2 |
D | A,B, C | 4 |
E | C,D | 5 |
F | A | 3 |
G | D,F | 6 |
H | E | 4 |
a. Draw a project network?
b. What are the critical activities
c. What activity has the most slack time?
d. Will the project be completed by September 1?
Price: $2.99
Solution: The solution consists of 2 pages
Deliverables: Word Document![](/images/msword.png)
Deliverables: Word Document
![](/images/msword.png)