A work center containing 4 machines of equal capability operates 2 shifts per day 5 days per week (8


Question: A work center containing 4 machines of equal capability operates 2 shifts per day 5 days per week (8 hours per shift). This is the effective capacity. If the work center has a system efficiency of 95%, what is the expected output in hours per week?

Price: $2.99
Solution: The solution consists of 1 page
Solution Format: Word Document