For the following project network, the times for each activity are listed in the table below. There
Question: For the following project network, the times for each activity are listed in the table below. There should be circles and arrows connecting some of the circles, in the diagram below. If these are not visible or did not print, please request assistance.
C
E
a. (30 points) Fill in the table with the correct ES, EF, LS, LF, and slack.
b. (5 points) Calculate the critical path. c. (5 points) Calculate the time to complete the project. |