Consider a network with 6 nodes (marked 1 to 6) and with 7 activities (marked A to G), as given in t
Question: Consider a network with 6 nodes (marked 1 to 6) and with 7 activities (marked A to G), as given in the following table
| ACTIVITIES | From node | To node | Durations | Preceded by activity |
| A | 1 | 2 | 10 | --? |
| B | 1 | 3 | 7 | --? |
| C | 2 | 3 | 5 | A |
| D | 2 | 4 | 13 | A |
| E | 3 | 5 | 4 | B, C |
| F | 4 | 6 | 12 | D |
| G | 5 | 6 | 14 | E |
a) Draw a diagram of this network
b) Determine the critical path through the network, and its total duration
c) Find out which activities have slack times, and what those times are.