Assume that the previous project has the following activity times (in months). Activity A B C
Question: Assume that the previous project has the following activity times (in months).
Activity | A | B | C | D | E | F | G |
Time | 4 | 6 | 2 | 6 | 3 | 3 | 5 |
A.) Find the critical path
B.) The project must be completed in 1 ½ years. Do you anticipate difficulty in meeting the deadline? Explain.
(previous problem information is below the project is complete when activities F and G are both complete).
Activity | A | B | C | D | E | F | G |
Immediate Predecessor | ----- | ----- | A | A | C,B | C,B | D,E |