Shirley Hopkins is developing a program in leadership training for middle-level managers


Question: (25 points) Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.

Activity Immediate Predecessor(s) Time (Days)
A ---- 2
B ---- 5
C ---- 1
D B 10
E A, D 3
F C 6
G E, F 8

a) Develop an AON or AOA network for this problem.


b) What is the critical path? What is the total project completion time?

c) What is the slack time for each activity?

d) Due to budget limitation, activity A, B, and D will be delayed for 2, 3, and 2 days, respectively. What is the completion date of the project in this case?

Price: $2.99
Solution: The solution consists of 4 pages
Deliverables: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in