Shirley Hopkins is developing a program in leadership training for middle-level managers
Question: (25 points) Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.
Activity | Immediate Predecessor(s) | Time (Days) |
A | ---- | 2 |
B | ---- | 5 |
C | ---- | 1 |
D | B | 10 |
E | A, D | 3 |
F | C | 6 |
G | E, F | 8 |
a) Develop an AON or AOA network for this problem.
![]() |
b) What is the critical path? What is the total project completion time?
c) What is the slack time for each activity?
d) Due to budget limitation, activity A, B, and D will be delayed for 2, 3, and 2 days, respectively. What is the completion date of the project in this case?