[Steps Shown] Using the assembly-line balancing procedure, what is the theoretical minimum number of workstations if the task times for the eight tasks


Question: Using the assembly-line balancing procedure, what is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3 and 6 minutes, and the cycle time is 8 minutes?