[Steps Shown] A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to


Question: A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

.:.

  1. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.
  2. Use the random numbers 0.1778, 0.9617, 0.6849, and 0.4503 to simulate the completion time of the project in weeks.
  3. Discuss how simulation could be used to estimate the probability the project can be completed in 35 weeks or less.