(See Solution) Jerry Casey wants to remodel his apartment. He listed the following activity times information for this project. Time is in days. Activity
Question:
Jerry Casey wants to remodel his apartment. He listed the following activity times information for this project. Time is in days.
| Activity | Description | Optimistic | Most probable | Pessimistic |
| A | Find interior designer | 2 | 3 | 4 |
| B | Develop design | 3 | 4 | 6 |
| C | Establish budget | 3 | 4 | 5 |
| D | Discard unwanted furniture | 1 | 2 | 3 |
| E | Remove floors | 3 | 5 | 7 |
| F | Work on bathrooms | 8 | 10 | 13 |
| G | Painting | 3 | 4 | 5 |
| H | Put new floors | 5 | 6 | 7 |
| I | Handle last-minute details | 2 | 2.5 | 3 |
- Compute the expected activity completion times and the variance for each activity.
- An analyst determined that the critical path consists of activities B-D-F. Compute the expected completion time and the variance.
Price: $2.99