[Step-by-Step] Given the line balance data: Task Predecessor Time in seconds t none 15 u t 14 v t 7 w u 6 x v 8 y w, x 10 z y 21 what is the minimum and
Question: Given the line balance data:
Task Predecessor Time in seconds
t none 15
u t 14
v t 7
w u 6
x v 8
y w, x 10
z y 21
- what is the minimum and maximum possible cycle time? what is the appropriate cycle time for 8 hrs of operating time per day and a desired output rate of 960 units per day?
- For 8 hrs of operating time per day and a desired output rate of 960 units per day, what is the minimum number of stations needed to achieve the appropriate cycle time?
- For 8 hrs of operating time per day and a desired output rate of 960 units per day, assign tasks to stations. (Assignment rule: assume indifference)
- For 8 hrs of operating time per day and a desired output rate of 960 units per day, what is the percentage of idle time for the balance which uses the minimum number of stations?
- For 8 hrs of operating time per day and a desired output rate of 960 units per day, what is the efficiency for the balance which uses the minimum number of stations?
Deliverable: Word Document 