[Steps Shown] Given the following information for a project, draw the AON (Activity-On -Node) project network. Activity Immediate Processor Activity Time


Question: Given the following information for a project, draw the AON (Activity-On -Node) project network.

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5

Price: $2.99
Solution: The downloadable solution consists of 1 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in