(See Steps) Given the following information for a project, What are the estimated slack times (in weeks) for activities A-H? Activity Immediate Processor


Question: Given the following information for a project, What are the estimated slack times (in weeks) for activities A-H?

Activity Immediate Processor Activity Time (days)
A - 6
B - 8
C A, B 5
D B 4
E C 7
F C, D 3
G D 6
H E, F, G 5

CP = Critical Path