[All Steps] Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors
Question: Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network:
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 4 | 8 | 12 |
| B | 6 | 7 | 8 |
| C | 6 | 12 | 18 |
| D | 3 | 5 | 7 |
| E | 6 | 9 | 18 |
| F | 5 | 8 | 17 |
| G | 10 | 15 | 20 |
| H | 5 | 6 | 13 |
- Find the critical path.
- What is the expected project completion time?
- What is the probability the project can he completed in the 44 weeks as requested by the owner?
- What is the probability the building project could run more than 3 months late? Use 47 weeks for this calculation.
- What should the construction company tell the owner?