(See Solution) the cycle time to carry out this task took 10 minutes. The evaluation of the worker's performance using a stopwatch was estimated at 110%.


Question: the cycle time to carry out this task took 10 minutes. The evaluation of the worker's performance using a stopwatch was estimated at 110%. The common practice in this department allows 5 minutes of personal time and 3 minutes of fatigue per hour.

additionally it is estimated that there should be an extra 2 minute allowance per hour.

  1. find the normal time "leveled" of the operation
  2. calculate the concession factor and the standard time of the operation