(Step-by-Step) Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7


Question: Consider the network described in the table below.

Activity Immediate
Predecessor(s)
Pessimistic Probable Optimistic
J -- 15 10 8
K -- 9 8 7
L J 10 6 5
M J 3 3 3
N K,M 9 5 1
O K,M 10 7 4
P L,N 10 8 3
  1. Calculate the expected duration of each activity.
  2. Calculate the expected duration and variance of the critical path.
  3. Calculate the probability that the project will be completed in fewer than 30 time units.

Price: $2.99
Solution: The downloadable solution consists of 2 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in