(Steps Shown) The city of Bloomington is about to build a new water treatment plant. Once the plant is designed (D) we can select the site (S), the building contractor
Question: The city of Bloomington is about to build a new water treatment plant. Once the plant is designed (D) we can select the site (S), the building contractor (C and the operating personnel (P). Once the site is selected we may erect the building (B). We can order the water treatment machine (W) and prepare the operations manual (M) only after the contractor is selected. We can begin training the operators (T) when both the operations manual and operating personnel selected are completed. When the water treatment and building are finished, we can install the treatment machine (I). Once the treatment machine is installed and the operators are trained, we can obtain an operating license (L). The time to complete each activity is assumed to be a normal distribution and the estimated mean and standard deviation of the time (in months) needed to complete each activity is defined below:
- Draw the PERT network for the project
- Calculate the critical path and estimated completion time of the project
- Using this estimated completion time, determine the probability of completing the project in (1) under 45 months and (2) over 50 months
- Use simulation to calculate the estimated completion time and to determine the probability of completing the project in (1) under 45 months and (2) over 50 months (use a monte carlo simulation of 200 repetitions)
- Explain why the answers to questions (b) and (c) may differ to that determined in question (d).
- Use simulation to estimate the probability that \(\mathrm{B}, \mathrm{I}\) and \(\mathrm{T}\) are critical activities
Deliverable: Word Document 