[Solution] If an activity cannot be delayed without affecting the entire project, then it is a __________ activity. completed critical crashed non-critical
Question: If an activity cannot be delayed without affecting the entire project, then it is a __________ activity.
- completed
- critical
- crashed
- non-critical
- normal
Price: $2.99