The time required to complete a project is normally distributed with a mean of 80 weeks and a standa
Question: The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks. The construction company must pay a penalty if the project is not finished by the dues date of the contract. If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date, what due date (project week #) should be negotiated?
Price: $2.99
Answer: The answer consists of 1 page
Deliverables: Word Document
Deliverables: Word Document
