The expected duration for a project is 64 days with a project variance of 36 days. a. Compute the p


Question: The expected duration for a project is 64 days with a project variance of 36 days.

a. Compute the probability of the project being completed in more than 60 days.

b. In less than 70 days.

c. Between 60 and 70 days.

Price: $2.99
Solution: The solution consists of 1 page