Davidson Construction Company is building a luxury lakefront home in the Finger Lakes region of New


Question: Davidson Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion data requested by the owner. The Davidson project manager prepared the following project network.

B
F


H

Start


Estimates of the optimistic, most probable and pessimistic times (in weeks) for the activities are as follows.

Activity Optimistic Most Probable Pessimistic
A 4 8 12
B 6 7 8
C 6 12 18
D 3 5 7
E 6 9 18
F 5 8 17
G 10 15 20
H 5 6 13

A.) Find the critical path

B.) What is the expected project completion time?

C.) What is the probability the project can be completed in the 44 weeks as requested by the owner?

D.) What is the probability the building project could run more than 3 months late? Use 57 weeks for this calculation.

E.) What should the construction company tell the owner?

Price: $2.99
Solution: The downloadable solution consists of 3 pages
Type of Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in