Davidson Construction Company is building a luxury lakefront home in the Finger Lakes region of New
Question: Davidson Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion data requested by the owner. The Davidson project manager prepared the following project network.
|
|
|
![]() | |||||||
![]() | |||||||
| |||||||
![]() | |||||||
Estimates of the optimistic, most probable and pessimistic times (in weeks) for the activities are as follows.
Activity | Optimistic | Most Probable | Pessimistic |
A | 4 | 8 | 12 |
B | 6 | 7 | 8 |
C | 6 | 12 | 18 |
D | 3 | 5 | 7 |
E | 6 | 9 | 18 |
F | 5 | 8 | 17 |
G | 10 | 15 | 20 |
H | 5 | 6 | 13 |
A.) Find the critical path
B.) What is the expected project completion time?
C.) What is the probability the project can be completed in the 44 weeks as requested by the owner?
D.) What is the probability the building project could run more than 3 months late? Use 57 weeks for this calculation.
E.) What should the construction company tell the owner?
Type of Deliverable: Word Document