Schotte Manufacturing Company uses two different independent variables (machine-hours and number of
Question: Schotte Manufacturing Company uses two different independent variables (machine-hours and number of packages) in two different equations to evaluate costs of the packaging department. The most recent results of the two regressions are as follows:
Machine-hours
Variable Coefficient Standard Error t-value
Constant $748.30 $341.20 2.19
Independent Variable $52.90 $35.20 1.50
r2=0.33
Number of packages:
Variable Coefficient Standard Error t-value
Constant $242.90 $75.04 3.24
Independent Variable $5.60 $2.00 2.80
r2=0.73
a- What are the estimating equations for each cost driver?
b- Which cost driver is best and why?