Consider the data in Problem 1, but suppose now that acidity C takes nine days to complete rather th
Question: Consider the data in Problem 1, but suppose now that acidity C takes nine days to complete rather than seven days.
a. Does the critical path change?
b. If activity C were to take 11 days to complete, would the critical path change?