The following are the activity times for the project in problem 214. Find the earliest latest and sl


Question: The following are the activity times for the project in problem 214. Find the earliest latest and slack times for each activity. Then find the critical path.

Activity Time (Days)
A 3
B 7
C 4
D 2
E 5
F 6
G 3