The following are the activity times for the project in problem 214. Find the earliest latest and sl
Question: The following are the activity times for the project in problem 214. Find the earliest latest and slack times for each activity. Then find the critical path.
Activity | Time (Days) |
A | 3 |
B | 7 |
C | 4 |
D | 2 |
E | 5 |
F | 6 |
G | 3 |