Sid Davidson was able to determine the activity times for the leadership training program. He would


Question: Sid Davidson was able to determine the activity times for the leadership training program. He would like to determine the total project completion tiMeand the critical path. The activity times appear in the following table (see problem 212 above)

Activity Time(Days)
A 2
B 5
C 1
D 10
E 3
F 6
G 8
35