Precision Manufacturing has a government contract to produce stainless steel rods for use in militar
Question: Precision Manufacturing has a government contract to produce stainless steel rods for use in military aircraft. Each rod is required to be 20 millimeters in diameter. Each hour, random samples of size n = 4 rods are measured to check process control. Five hours of observations yielded the following:
| Diameter | ||||
| Time | Rod 1 | Rod 2 | Rod 3 | Rod 4 |
| 9 A.M. | 19.8 | 20.4 | 19.9 | 20.3 |
| 10 A.M. | 20.1 | 20.2 | 19.9 | 19.8 |
| 11 A.M. | 19.9 | 20.5 | 20.3 | 20.1 |
| Noon | 19.7 | 19.8 | 20.3 | 20.2 |
| 1 P.M. | 19.7 | 20.1 | 19.9 | 19.9 |
Using these data and the table below, construct limits for xbar- and R-charts. Is the process in control?
| Control Chart Limits Factors | |||
| Sample Size n | Mean Factor A2 | Upper Range D4 | Lower Range D3 |
| 2 | 1.880 | 3.628 | 0 |
| 3 | 1.023 | 2.574 | 0 |
| 4 | 0.729 | 2.282 | 0 |
| 5 | 0.577 | 2.114 | 0 |
| 6 | 0.483 | 2.004 | 0 |
| 7 | 0.419 | 1.924 | 0.076 |
| 8 | 0.373 | 1.864 | 0.136 |
| 9 | 0.337 | 1.816 | 0.184 |
| 10 | 0.308 | 1.777 | 0.223 |
| 12 | 0.266 | 1.716 | 0.284 |