Question: The following represents a project with known activity times. All times are in weeks.

Activity Immediate Predecessor Time
A - 4
B - 3
C A 2
D B 7
E C, D 4
F B 5

a. What is the minimum possible time required for completing the project?

b. What is the latest possible time that Activity C may be started without delaying the completion of the project?

c. What is the slack time for Activity D?

d. What is the latest finish time for Activity E?