The following represents a project with known activity times. All times are in weeks. Activity
Question: The following represents a project with known activity times. All times are in weeks.
Activity | Immediate Predecessor | Time |
A | - | 4 |
B | - | 3 |
C | A | 2 |
D | B | 7 |
E | C, D | 4 |
F | B | 5 |
a. What is the minimum possible time required for completing the project?
b. What is the latest possible time that Activity C may be started without delaying the completion of the project?
c. What is the slack time for Activity D?
d. What is the latest finish time for Activity E?