[Solution] Use the following network with activities and times estimated in days to answer questions a through c. (Worth 7-points) Activity Optimistic Most


Question: Use the following network with activities and times estimated in days to answer questions a through c. (Worth 7-points)


Activity Optimistic Most
Probable
Pessimistic
A 2 5 6
B 1 3 7
C 6 7 10
D 5 12 14
E 3 4 5
F 8 9 12
G 4 6 8
H 3 6 8
I 5 7 12
J 12 13 14
K 1 3 4

  1. What are the critical path activities?
  2. What is the expected time to complete the project?
  3. What is the probability the project will take more than 28 days to complete?

Price: $2.99
Solution: The downloadable solution consists of 3 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in