[Solution] Use the following network with activities and times estimated in days to answer questions a through c. (Worth 7-points) Activity Optimistic Most
Question:
Use the following network with activities and times estimated in days to answer questions a through c.
(Worth 7-points)
| Activity | Optimistic |
Most
Probable |
Pessimistic |
| A | 2 | 5 | 6 |
| B | 1 | 3 | 7 |
| C | 6 | 7 | 10 |
| D | 5 | 12 | 14 |
| E | 3 | 4 | 5 |
| F | 8 | 9 | 12 |
| G | 4 | 6 | 8 |
| H | 3 | 6 | 8 |
| I | 5 | 7 | 12 |
| J | 12 | 13 | 14 |
| K | 1 | 3 | 4 |
- What are the critical path activities?
- What is the expected time to complete the project?
- What is the probability the project will take more than 28 days to complete?