[Solved] The table below show the Present value and the present value of several projects Project PV NPV A 500,000 50,000 B 200,000 40,000 C 300,000 50,000


Question: The table below show the Present value and the present value of several projects

Project PV NPV
A 500,000 50,000
B 200,000 40,000
C 300,000 50,000
  1. Calculate the profitability index for each investment. (4 marks)
  2. Rank the project in order of the preference. (1 marks)

Price: $2.99