[See Steps] A software development company wants to assign 4 software engineers to four projects. The estimated time of completion (in days) of each project


Question: A software development company wants to assign 4 software engineers to four projects. The estimated time of completion (in days) of each project by each software engineer is given in the following table.

Project 1 Project 2 Project 3 Project 4

___________________________________________________________

Software Engineer A 28 25 20 18

Software Engineer B 40 32 - 44

Software Engineer C 36 27 19 25

Software Engineer D 30 25 15 22

___________________________________________________________

Software engineer B cannot be assigned to project 3 because he does not have enough training to do that project. The company wants project 1 to be assigned to software engineer C or software engineer D. The objective is to minimize the total time of completion of all four projects.

For this assignment problem:

  1. Define the decision variables.

(b) Determine the objective function. What does it represent?

(c) Determine all the constraints. Briefly describe what each constraint represents.

Note: Do NOT solve the problem after formulating.

Price: $2.99
Solution: The downloadable solution consists of 2 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in