(Step-by-Step) Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must
Question: (25 points) Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.
| Activity | Immediate Predecessor(s) | Time (Days) |
| A | ---- | 2 |
| B | ---- | 5 |
| C | ---- | 1 |
| D | B | 10 |
| E | A, D | 3 |
| F | C | 6 |
| G | E, F | 8 |
- Develop an AON or AOA network for this problem.
- What is the critical path? What is the total project completion time?
- What is the slack time for each activity?
- Due to budget limitation, activity A, B, and D will be delayed for 2, 3, and 2 days, respectively. What is the completion date of the project in this case?